Bitcoin miners and the grid connections AI wants
An AI data center needs steady electricity to run servers and remove the heat they produce. A new site must wait until the grid can serve the load. Bitcoin miners already connected some large sites, which can save time if their connection terms and location suit a new customer. The building, cooling, network and backup power still have to meet the customer’s needs.
Thesis
Existing grid connections can shorten the time to open an AI data center. The commercial evidence comes in stages: an energized site, a binding tenant contract, construction and commissioning, then billing. A megawatt at one stage is worth something different from a megawatt at another.
November 14, 2026 update. Riot’s November 4 release confirmed a 15-year Corsicana powered-land lease for 910 MW of critical computing load and about $28 billion of contracted revenue over the initial term. The figure spans the lease term and deployment is phased. Core Scientific’s filing showed 485 MW had begun billing at September 30. MARA’s letter sets out a development path with Starwood, and Bitdeer’s November 10 results describe its AI cloud business. We found no signed AI tenant lease for the MARA sites discussed here or for Bitdeer’s Rockdale site in those releases.
Backdrop — How Miners Ended Up Owning the Scarce Input
Bitcoin mining is a race to guess a number, and the machine that guesses fastest per unit of electricity wins a share of 3.125 new bitcoin every ten minutes. Because electricity is most of the cost, miners spent the last cycle buying cheap power at industrial scale: Texas sites behind wind farms, Ohio and Pennsylvania sites inside the PJM market, hydro in Québec, Paraguay and Bhutan. They took grid connections that utilities were happy to grant, because a miner agrees to shut down when the grid is stressed. Riot cut its draw by more than 95% during an August 2023 heat wave and was paid by the grid for doing so.
A miner that already has power can be a candidate for conversion. Mining tolerates interruptions more easily than many AI workloads, so the grid agreement and backup design can determine whether the site works.
Core Scientific’s quarterly filing shows the transition can change the revenue mix once customers begin paying. Around $215.4 million of $232.9 million in Q3 2026 revenue came from colocation, or 92.5%. A year earlier self-mining was the biggest source of revenue.
Mechanism — Why Now & How It Works
A grid connection is slow because it is shared. When a 300 MW load asks to connect, the operator has to prove that every line and transformer between it and the generators can carry the extra current on the hottest day, with one major line out of service. If not, someone pays for new transmission or a new substation, each of which takes two to five years and a public permit. In Texas, Senate Bill 6 (2025) made loads of 75 MW or more subject to new interconnection standards that the state regulator adopted in September 2026, and ERCOT has been studying a "Batch Zero" group of large loads at once. On 3 August 2026 the governor ordered a verification audit of data-center projects; ERCOT's 5 November update still targets 10 December. A wire that is already live skips all of that.
What carries over, and what does not. The substation, the transmission tap and the land carry over. Almost everything behind the fence does not. A mine is a Tier I building on purpose: fans, single power paths, no batteries, because a pause costs nothing. An AI hall needs Tier III, meaning any part can be repaired without shutting the room: two independent power paths, batteries and generators or an equivalent, and liquid cooling piped to the chips, plus diverse fiber routes. Core Scientific's Denton campus took about two years from the first CoreWeave contract to 260 MW billing, a delay Global Data Center Hub traced through the company's own filings.
The conversion costs money in two very different amounts. Riot's Corsicana lease is a powered-land deal: Riot delivers land, high- and medium-voltage gear and powered pads, the tenant brings modular data halls and chips, and the all-in capital is about $6M per IT MW, half of a Tier III build in Riot's own words. CleanSpark is building Sandersville for Meta at about $11.9M per IT MW. Galaxy's Helios Phase I for CoreWeave cost $1.8B for 133 IT MW, about $13.5M per IT MW, because Galaxy built the full shell.
A site’s utility capacity includes cooling and other building loads. The usable computing load is smaller. Galaxy’s example is about 200 MW from the utility for 133 MW of computing load, a ratio of 1.50. CleanSpark’s Sandersville design uses about 250 MW for 175 MW, a ratio of 1.43. Riot describes about 1,000 MW of utility capacity and 910 MW of computing load at Corsicana, a ratio of 1.10. Each design has its own requirements.
Interruptibility is the one feature that does not transfer. A miner's power contract often pays it to curtail, and some miners hold fixed-price power for a fixed volume. An AI tenant wants firm power around the clock. Some sites can only be firmed with on-site generation, which in Texas now needs an air permit that the governor paused in September. Where a miner's contract is firm, as at Riot's Corsicana campus, the megawatt converts at close to full value. Where it was granted as interruptible load, the tenant pays for the difference in batteries, gas turbines or a new study.
What the customer pays for
Annual revenue per megawatt is useful only if the service and the denominator match. A powered-land landlord, a data hall operator and a company selling computing time deliver different things and carry different equipment costs.
A computing provider buys accelerators, funds replacement cycles and bears utilization risk. A powered-land lease shifts much of that spending to the tenant. Even within real estate deals, annual rent, net operating income and total contract value measure different things.
How capacity reaches a customer
Leases let a tenant secure a site and a delivery timetable while the owner retains the rest of its business. A joint venture can share development costs. In either case the parties need to agree on construction, power and financing before the site can begin billing.
Who controls the sites
The site inventory below distinguishes operating mining sites, leased data-center capacity and development plans. The presence of a connection alone does not establish that an AI customer can use all of it.
$MARA. Its Q3 shareholder letter describes roughly 1 GW of owned and operated capacity. Management is pursuing tenant agreements through the Starwood venture. Future projects and hosted mining arrangements are separate from those owned sites.
$BTDR. Bitdeer’s Q3 report says it is evaluating an AI transition at Rockdale. AI cloud contracts elsewhere do not establish that a Rockdale tenant has signed. Its financing costs and equipment spending matter even if the site proves attractive.
$CLSK. CleanSpark’s presentation separates the signed Sandersville lease from the Texas portfolio subject to exclusivity. The signed facility and the other sites are at different commercial stages.
$KEEL — no mining, no tenant, a balance sheet to wait. Bitfarms renamed itself Keel Infrastructure, stopped US mining on 29 June and holds $816M of cash against $1.05B of debt. Its near-term 478 MW at Moses Lake, Sharon and Panther Creek gets substations in 2027, and it reports 341 MW energized today (10-Q).
$HIVE — mostly Paraguayan hydro. About 300 MW sits in Paraguay, where an AI tenant is unlikely soon; the AI case is the ~140 MW in Canada and Sweden plus 400 MW of Canadian load earmarked for Tier III (Q2 FY27 release).
Risks and evidence to watch
An interruptible mining connection may need additional approvals or backup before it can serve continuous computing. Build costs, financing, permitting, tenant credit and delayed billing can all reduce returns. Capacity in early development should be valued separately from energized sites and contracted rent.
How to value the opportunity
The operating transition is visible at Core Scientific and the contracted opportunity is visible at Riot. At MARA and Rockdale, much of the case still depends on a tenant signing, a feasible construction budget and delivery. The most informative milestones are binding contracts, funding, completed facilities and the first bills paid by customers.